Introduction
The Risk Management process
Risk issues
Modelling
Events
Networks and branching
Other
All risks within a project will impact on one of cost, schedule timing or revenue.
The problem with any project is the status quo. The project team may tend to consider the plan rather simplistically in that they will know where the risks exist and approach allocation of resource on this basis.
Another problem is the detail of the project plans that will be generated. These will start from the top down. How far do we go down and to what level of detail do we go? The key aspect here is what can we manage? Also, consider horizon planning later.
If you can’t manage it don’t do it. Also, to generate this amount of detail costs TIME.
By utilising simple risk assessment techniques we will gain a better idea of where the main risk areas are and hence where to put the resource.
Introduction
Definition [see Introduction part 1]
Terminology [see Introduction part 2]
What is a project? Scope [see Introduction part 3]
The processes [see Introduction part 4]
Introduction to processes [see Introduction to processes]
The components [see The components]
Managing Stage Boundaries
Fundamental principles [see Managing Stage Boundaries (SB) part 1]
Planning a Stage [see Managing Stage Boundaries (SB) part 2]
Updating a Project Plan [see Managing Stage Boundaries (SB) part 3]
Updating a Project Business Case [see Managing Stage Boundaries (SB) part 4]
Updating the Risk Log [see Managing Stage Boundaries (SB) part 5]
Reporting Stage End [see Managing Stage Boundaries (SB) part 6]
Producing an Exception Plan [see Managing Stage Boundaries (SB) part 7]
Plans
What is a plan? [see Plans part 1]
Levels of plan [see Plans part 2]
Introduction
Foreword [see Foreword]
Purpose [see Introduction part 1]
What does a project manager do? [see Introduction part 2a]
What is it we wish to control? [see Introduction part 2b]
The structure of PRINCE2 [see Introduction part 2c]
What PRINCE2 does not provide [see Introduction part 3]
Plans
Purpose [see Plans - Purpose]
What is a plan? [see Plans - Plans defined - What is a plan?]
What is planning? [see Plans - Plans defined - What is planning?]
Levels of plan [see Plans - Plans defined - Levels of plan]
The Project Plan [see Plans - Plans defined - The Project Plan]
Stage Plans [see Plans - Plans defined - Stage Plans]
Team Plans [see Plans - Plans defined - Team Plans]
Exception Plans [see Plans - Plans defined - Exception Plans]
Philosophy [see Plans - The PRINCE2 approach - Philosophy]
Prerequisites for planning - design the plan [see Plans - The PRINCE2 approach - Prerequisites for planning - design the plan]
Define and analyse the products [see Plans - The PRINCE2 approach - Define and analyse the products]
Write the Project Product Description [see Plans - The PRINCE2 approach - Prerequisites for planning - design the plan - Write the Project Product Description]
Create the product breakdown structure [see Plans - The PRINCE2 approach - Prerequisites for planning - design the plan - Create the product breakdown structure]
Write the Product Descriptions [see Plans - The PRINCE2 approach - Prerequisites for planning - design the plan - Write the Product Descriptions]
Create the product flow diagram [see Plans - The PRINCE2 approach - Prerequisites for planning - design the plan - Create the product flow diagram]
Activities [see Plans - The PRINCE2 approach - Identify activities and dependencies - Activities]
Dependencies [see Plans - The PRINCE2 approach - Identify activities and dependencies - Dependencies]
Prepare estimates [see Plans - The PRINCE2 approach - Prepare estimates]
Prepare the schedule [see Plans - The PRINCE2 approach - Prepare the schedule]
Define activity sequence [see Plans - The PRINCE2 approach - Prepare the schedule - Define activity sequence]
Assess resource availability [see Plans - The PRINCE2 approach - Prepare the schedule - Assess resource availability]
Assign resources [see Plans - The PRINCE2 approach - Prepare the schedule - Assign resources]
Level resource usage [see Plans - The PRINCE2 approach - Prepare the schedule - Level resource usage]
Agree control points [see Plans - The PRINCE2 approach - Prepare the schedule - Agree control points]
Define milestones [see Plans - The PRINCE2 approach - Prepare the schedule - Define milestones]
Calculate total resource requirements and costs [see Plans - The PRINCE2 approach - Prepare the schedule - Calculate total resource requirements and costs]
Analyse the risks [see Plans - The PRINCE2 approach - Analyse the risks]
Document the plan [see Plans - The PRINCE2 approach - Document the plan]
Responsibilities [see Plans - Responsibilities]
Managing a stage boundary
Purpose [see Managing a Stage Boundary - Purpose]
Objective [see Managing a Stage Boundary - Objective]
Objective 2 [see Managing a Stage Boundary - Objective 2]
Activities [see Managing a Stage Boundary - Activities]
Plan the next stage [see Managing a Stage Boundary - Plan the next stage]
Update the Project Plan [see Managing a Stage Boundary - Activities - Update the Project Plan]
Update the Business Case [see Managing a Stage Boundary - Activities - Update the Business Case]
Report stage end [see Managing a Stage Boundary - Activities - Report stage end]
Produce an Exception Plan [see Managing a Stage Boundary - Activities - Produce an Exception Plan]
Risk
Purpose [see Risk - Purpose]
What is a risk? [see Risk - Risk defined - What is a risk?]
What is at risk? [see Risk - Risk defined - What is at risk?]
What is risk management? [see Risk - Risk defined - What is risk management?]
Management of Risk (MoR) principles [see Risk - The PRINCE2 approach - Management of Risk (MoR) principles]
Risk management in projects [see Risk - The PRINCE2 approach - Risk management in projects]
Risk Management Strategy [see Risk - The PRINCE2 approach - Risk Management Strategy]
Risk Register [see Risk - The PRINCE2 approach - Risk Register]
Risk management procedure [see Risk - The PRINCE2 approach - Risk management procedure]
Risk management procedure - Identify part 1 [see Risk - The PRINCE2 approach - Risk management procedure - Identify part 1]
Risk management procedure - Identify part 2 [see Risk - The PRINCE2 approach - Risk management procedure - Identify part 2]
Risk management procedure - Assess [see Risk - The PRINCE2 approach - Risk management procedure - Assess]
Risk management procedure - Plan [see Risk - The PRINCE2 approach - Risk management procedure - Plan]
Risk management procedure - Implement [see Risk - The PRINCE2 approach - Risk management procedure - Implement]
Risk management procedure - Communicate [see Risk - The PRINCE2 approach - Risk management procedure - Communicate]
Risk budget [see Risk - Risk - The PRINCE2 approach - Risk budget]
Responsibilities [see Risk - Responsibilities]
Introduction
What is a project? [see What is a project?]
What is project management? [see What is project management?]
Project management system [see What does a project management system consist of?]
Project visualisation [see Project visualisation]
Work breakdown [see Why breakdown a project?]
Concept [see Concept or idea]
Feasibility [see Feasibility study]
Initiation [see Initiation]
Specification [see Specification]
Project management design [see Design]
Project management build [see Build]
Project management implementation [see Implementation]
Project management operation and review [see Operation and review]
The Project Notebook [see The Project Notebook]
Plans
Planning [see Planning - part 1]
Planning [see Planning - part 2 – Introduction - need to answer]
Planning [see Planning - part 3 - Introduction - schedule overview]
Plans [see Types of plans]
Detailed planning
Planning [see Detailed planning – part 1]
Estimation [see Detailed planning – part 2 - Initial estimation - simple cost plan]
Estimation [see Detailed planning – part 3 - Initial estimation - high level plan (first review)]
Estimation [see Detailed planning – part 4 - Initial estimation - high level plan (second review)]
Estimation [see Detailed planning – part 5 - Initial estimation - budget cost plan]
Estimating [see Detailed planning – part 6 - Estimating - overview]
Estimating [see Detailed planning – part 7 - Estimating - why are estimates too long?]
Estimating [see Detailed planning – part 8 - Estimating - why are estimates too short?]
Estimating [see Detailed planning – part 9 - Estimating - data usage]
Dependencies [see Detailed planning – part 10 - Dependencies (4 basic types)]
Dependencies [see Detailed planning – part 11 - Dependencies (4 basic types)]
Critical path [see Detailed planning – part 12]
PERT [see Detailed planning – part 12]
Slack and float [see Detailed planning – part 12]
PERT [see Detailed planning – part 13 – PERT – part 1]
PERT [see Detailed planning – part 14 – PERT – part 2]
PERT [see Detailed planning – part 15 – PERT – part 3 - Cumulative Probability graph]
Elapsed time [see Detailed planning – part 16]
Roles and responsibilities [see Detailed planning – part 17]
Responsibilities and resources [see Detailed planning - part 18 - Responsibilities and resources]
Gantt chart [see Detailed planning – part 19]
Constraints [see Detailed planning – part 20]
Critical path [see Detailed planning – part 21 - Critical path – part 1]
Critical path [see Detailed planning – part 22 - Critical path – part 2 - choosing one]
Critical path [see Detailed planning – part 23 - Critical path – part 3 - eliminating one]
Critical path [see Detailed planning – part 24 - Critical path – part 3 - reducing durations]
Risk management
Risk management [see Risk management – part 1 - Overview]
Risk management [see Risk management part 2 – General approach]
Risk management [see Risk management part 3 – Methods of assessing risk]
Health and safety [see Health and safety]
Introduction
Resources [see Resources]
Workaholic [see Workaholic]
What is time management? [see What is time management? Problem Time solving]
What is time management? [see What is time management? General]
Human issues
Human nature [see Human nature]
Blame culture [see Blame culture]
Stress [see Stress]
Stress sources [see Stress sources]
Stress problems [see Stress problems]
Coping with stress [see Coping with stress]
Playtime [see Playtime]
Styles
Time [see Time]
Monochronic time [see Monochronic time]
Polychronic time [see Polychronic time]
High and low context culture [see High and low context culture]
Divergent thinking [see Divergent thinking]
Convergent thinking [see Convergent thinking]
Blending styles [see Blending styles]
Personality drivers [see Personality drivers]
Assertiveness [see Assertiveness]
Delegation
People [see People]
Poor delegation and the Team [see Poor delegation and the Team]
Delegation process [see Delegation process]
Delegation towards independence [see Delegation towards independence]
What not to do [see What not to do]
Key time destroyers
Key Time Destroyers [see Key Time Destroyers]
Action chasing [see Action chasing]
Being disorganised [see Being disorganised]
Cant say 'No' [see Cant say 'No']
Crisis management [see Crisis management]
Desktop management [see Desktop management]
Friends [see Friends]
Large reports [see Large reports]
Low energy levels [see Low energy levels]
Meetings 1 [see Meetings 1]
Meetings 2 [see Meetings 2]
Multiple tasks [see Multiple tasks]
Others errors [see Others errors]
Other's jobs [see Other's jobs]
Paperwork [see Paperwork]
Perfection [see Perfection]
Poor communication [see Poor communication]
Poor control and reporting [see Poor control and reporting]
Poor delegation [see Poor delegation]
Poor information [see Poor information]
Poor leadership [see Poor leadership]
Poor planning [see Poor planning]
Poor preparation [see Poor preparation]
Poor self discipline [see Poor self discipline]
Putting things off [see Putting things off]
Resource issues [see Resource issues]
Responsibility, accountability and authority [see Responsibility, accountability and authority]
Socialising [see Socialising]
Staff issues [see Staff issues]
The boss [see The boss]
The telephone 1 [see The telephone 1]
The telephone 2 [see The telephone 2]
Travel time [see Travel time]
Unfinished tasks [see Unfinished tasks]
Unwanted callers [see Unwanted callers]
Work overload [see Work overload]
Your own errors [see Your own errors]
Introduction
Definition of leadership [see Definition of leadership]
Leadership and effectiveness [see Leadership and effectiveness]
Leadership qualities [see Leadership qualities]
Leadership functions [see Leadership functions]
other sites of interest in the series
© Copyright 2011 all rights reserved March Limited
