Introduction
The Risk Management process
Risk issues
Modelling
Events
Networks and branching
Other
At this stage, much more resource is employed as the BASIC PLAN gets underway. The costs will begin to escalate.
In terms of project RISK the biggest weakness will be the management and control systems.
At this stage, ideally, the base plan contains reactive mitigating activities for particular identified risks together with triggers for contingency plans.
Any modifications arising from the earlier stages, e.g. design, could have a detrimental affect in the plan execution stage.
This could result not only in time delays but will almost certainly increase costs.
Some consideration and modification of the plan is almost inevitable.
Plans rarely if ever go as we would wish.
Any modifications to the plan should be assessed for RISK implications.
However, some of the problems will be RISKS that have not been identified in the earlier stages and are now coming to fruition.
A more detailed treatment of the planning and execution phases looking at objectives, milestones and many other aspects is covered in 'The Complete Project Management [see ‘The Complete Project Management package’] and [see 'The Complete Project Management plus PRINCE2'] Package' in this series.
Introduction
Definition [see Introduction part 1]
Terminology [see Introduction part 2]
What is a project? Scope [see Introduction part 3]
The processes [see Introduction part 4]
Introduction to processes [see Introduction to processes]
The components [see The components]
Plans
What is a plan? [see Plans part 1]
Levels of plan [see Plans part 2]
Controlling a Stage
Fundamental principles [see Controlling a Stage (CS) part 1]
Authorising Work Package [see Controlling a Stage (CS) part 2]
Assessing Progress [see Controlling a Stage (CS) part 3]
Capturing Project Issues [see Controlling a Stage (CS) part 4]
Examining Project Issues [see Controlling a Stage (CS) part 5]
Reviewing Stage Status [see Controlling a Stage (CS) part 6]
Reporting Highlights [see Controlling a Stage (CS) part 7]
Taking Corrective Action [see Controlling a Stage (CS) part 8]
Escalating Project Issues [see Controlling a Stage (CS) part 9]
Receiving Completed Work Package [see Controlling a Stage (CS) part 10]
Controls
Overview [see Controls part 1]
Project start-up [see Controls part 2]
Tolerance [see Controls part 3]
Product Descriptions [see Controls part 4]
Reports and assessment [see Controls part 5]
Controlled close [see Controls part 6]
Quality
What is quality? [see Quality in a Project Environment]
Purpose and definition [see Configuration management part 1]
Configuration control [see Configuration management part 2]
Project Issue management [see Change control]
Product-based planning [see The techniques]
Benefits [see Product based planning part 1]
Producing a Product Breakdown Structure [see Product based planning part 2]
Writing a Product Description and its contents [see Product based planning part 3]
Creating a Product Flow Diagram [see Product based planning part 4]
Change control steps [see Change control technique]
Overview of the technique [see Quality review technique part 1]
Steps in a formal quality review procedure [see Quality review technique part 2]
Introduction
Foreword [see Foreword]
Purpose [see Introduction part 1]
What does a project manager do? [see Introduction part 2a]
What is it we wish to control? [see Introduction part 2b]
The structure of PRINCE2 [see Introduction part 2c]
What PRINCE2 does not provide [see Introduction part 3]
Plans
Purpose [see Plans - Purpose]
What is a plan? [see Plans - Plans defined - What is a plan?]
What is planning? [see Plans - Plans defined - What is planning?]
Levels of plan [see Plans - Plans defined - Levels of plan]
The Project Plan [see Plans - Plans defined - The Project Plan]
Stage Plans [see Plans - Plans defined - Stage Plans]
Team Plans [see Plans - Plans defined - Team Plans]
Exception Plans [see Plans - Plans defined - Exception Plans]
Philosophy [see Plans - The PRINCE2 approach - Philosophy]
Prerequisites for planning - design the plan [see Plans - The PRINCE2 approach - Prerequisites for planning - design the plan]
Define and analyse the products [see Plans - The PRINCE2 approach - Define and analyse the products]
Write the Project Product Description [see Plans - The PRINCE2 approach - Prerequisites for planning - design the plan - Write the Project Product Description]
Create the product breakdown structure [see Plans - The PRINCE2 approach - Prerequisites for planning - design the plan - Create the product breakdown structure]
Write the Product Descriptions [see Plans - The PRINCE2 approach - Prerequisites for planning - design the plan - Write the Product Descriptions]
Create the product flow diagram [see Plans - The PRINCE2 approach - Prerequisites for planning - design the plan - Create the product flow diagram]
Activities [see Plans - The PRINCE2 approach - Identify activities and dependencies - Activities]
Dependencies [see Plans - The PRINCE2 approach - Identify activities and dependencies - Dependencies]
Prepare estimates [see Plans - The PRINCE2 approach - Prepare estimates]
Prepare the schedule [see Plans - The PRINCE2 approach - Prepare the schedule]
Define activity sequence [see Plans - The PRINCE2 approach - Prepare the schedule - Define activity sequence]
Assess resource availability [see Plans - The PRINCE2 approach - Prepare the schedule - Assess resource availability]
Assign resources [see Plans - The PRINCE2 approach - Prepare the schedule - Assign resources]
Level resource usage [see Plans - The PRINCE2 approach - Prepare the schedule - Level resource usage]
Agree control points [see Plans - The PRINCE2 approach - Prepare the schedule - Agree control points]
Define milestones [see Plans - The PRINCE2 approach - Prepare the schedule - Define milestones]
Calculate total resource requirements and costs [see Plans - The PRINCE2 approach - Prepare the schedule - Calculate total resource requirements and costs]
Analyse the risks [see Plans - The PRINCE2 approach - Analyse the risks]
Document the plan [see Plans - The PRINCE2 approach - Document the plan]
Responsibilities [see Plans - Responsibilities]
Risk
Purpose [see Risk - Purpose]
What is a risk? [see Risk - Risk defined - What is a risk?]
What is at risk? [see Risk - Risk defined - What is at risk?]
What is risk management? [see Risk - Risk defined - What is risk management?]
Management of Risk (MoR) principles [see Risk - The PRINCE2 approach - Management of Risk (MoR) principles]
Risk management in projects [see Risk - The PRINCE2 approach - Risk management in projects]
Risk Management Strategy [see Risk - The PRINCE2 approach - Risk Management Strategy]
Risk Register [see Risk - The PRINCE2 approach - Risk Register]
Risk management procedure [see Risk - The PRINCE2 approach - Risk management procedure]
Risk management procedure - Identify part 1 [see Risk - The PRINCE2 approach - Risk management procedure - Identify part 1]
Risk management procedure - Identify part 2 [see Risk - The PRINCE2 approach - Risk management procedure - Identify part 2]
Risk management procedure - Assess [see Risk - The PRINCE2 approach - Risk management procedure - Assess]
Risk management procedure - Plan [see Risk - The PRINCE2 approach - Risk management procedure - Plan]
Risk management procedure - Implement [see Risk - The PRINCE2 approach - Risk management procedure - Implement]
Risk management procedure - Communicate [see Risk - The PRINCE2 approach - Risk management procedure - Communicate]
Risk budget [see Risk - Risk - The PRINCE2 approach - Risk budget]
Responsibilities [see Risk - Responsibilities]
Managing a stage boundary
Purpose [see Managing a Stage Boundary - Purpose]
Objective [see Managing a Stage Boundary - Objective]
Objective 2 [see Managing a Stage Boundary - Objective 2]
Activities [see Managing a Stage Boundary - Activities]
Plan the next stage [see Managing a Stage Boundary - Plan the next stage]
Update the Project Plan [see Managing a Stage Boundary - Activities - Update the Project Plan]
Update the Business Case [see Managing a Stage Boundary - Activities - Update the Business Case]
Report stage end [see Managing a Stage Boundary - Activities - Report stage end]
Produce an Exception Plan [see Managing a Stage Boundary - Activities - Produce an Exception Plan]
Introduction
What is a project? [see What is a project?]
What is project management? [see What is project management?]
Project management system [see What does a project management system consist of?]
Project visualisation [see Project visualisation]
Work breakdown [see Why breakdown a project?]
Concept [see Concept or idea]
Feasibility [see Feasibility study]
Initiation [see Initiation]
Specification [see Specification]
Project management design [see Design]
Project management build [see Build]
Project management implementation [see Implementation]
Project management operation and review [see Operation and review]
The Project Notebook [see The Project Notebook]
Mission statement
Mission statement [see Mission statement]
Mission statement Simple [see Mission statement Simple approach]
Mission statement Formal [see Mission statement Formal approach]
Objectives
Objectives [see Objectives – part 1 - Reasons for setting]
Objectives [see Objectives – part 2 – Should be]
Milestones
Milestones [see Milestones – part 1 - General]
Milestones [see Milestones – part 2 - Deliverables]
Project control
Why? What can go wrong? [see Control – part 1 - Why? What can go wrong?]
Monitoring [see Control – part 2 - Monitoring]
General [see Control – part 3 - General]
Scope [see Control – part 4 - What? - scope]
Time [see Control – part 5 - Time]
Cost [see Control – part 6 - Cost]
Cost - common terms [see Control – part 7 - Cost - common terms]
Cost - overspend [see Control – part 8 - Cost - overspend]
Cost - cash flow [see Control – part 9 - Cost - cash flow]
Progress reporting - general [see Control – part 10 - Progress reporting - general]
Progress reporting - Project Board [see Control – part 11 - Progress reporting - Project Board]
Progress reporting - what data? [see Control – part 12 - Progress reporting - what data?]
Taking action - what does this entail? [see Control – part 13 - Taking action - what does this entail?]
Assessing the situation [see Control – part 14 - Assessing the situation]
Resolving issues and problems [see Control – part 15 - Resolving issues and problems]
Contingency [see Control – part 16 - Contingency]
Areas of review [see Control – part 17 - Areas of review]
Controlling change – part 1 [see Control – part 18 - Controlling change – part 1]
Controlling change – part 2 [see Control – part 19 - Controlling change – part 2]
Document control procedures [see Control – part 20 - Document control procedures]
Project completion [see Control – part 21 - Project completion]
Risk management
Risk management [see Risk management – part 1 - Overview]
Risk management [see Risk management part 2 – General approach]
Risk management [see Risk management part 3 – Methods of assessing risk]
Health and safety [see Health and safety]
Introduction
Resources [see Resources]
Workaholic [see Workaholic]
What is time management? [see What is time management? Problem Time solving]
What is time management? [see What is time management? General]
Goals
Goals 1 [see Goals 1]
Goals 2 [see Goals 2]
Objectives
Objectives [see Objectives]
Prioritising objectives part 1 [see Prioritising objectives 1]
Prioritising objectives part 2 [see Prioritising objectives 2]
Prioritising objectives part 3 [see Prioritising objectives 3]
Human issues
Human nature [see Human nature]
Blame culture [see Blame culture]
Stress [see Stress]
Stress sources [see Stress sources]
Stress problems [see Stress problems]
Coping with stress [see Coping with stress]
Playtime [see Playtime]
Styles
Time [see Time]
Monochronic time [see Monochronic time]
Polychronic time [see Polychronic time]
High and low context culture [see High and low context culture]
Divergent thinking [see Divergent thinking]
Convergent thinking [see Convergent thinking]
Blending styles [see Blending styles]
Personality drivers [see Personality drivers]
Assertiveness [see Assertiveness]
Delegation
People [see People]
Poor delegation and the Team [see Poor delegation and the Team]
Delegation process [see Delegation process]
Delegation towards independence [see Delegation towards independence]
What not to do [see What not to do]
Key time destroyers
Key Time Destroyers [see Key Time Destroyers]
Action chasing [see Action chasing]
Being disorganised [see Being disorganised]
Cant say 'No' [see Cant say 'No']
Crisis management [see Crisis management]
Desktop management [see Desktop management]
Friends [see Friends]
Large reports [see Large reports]
Low energy levels [see Low energy levels]
Meetings 1 [see Meetings 1]
Meetings 2 [see Meetings 2]
Multiple tasks [see Multiple tasks]
Others errors [see Others errors]
Other's jobs [see Other's jobs]
Paperwork [see Paperwork]
Perfection [see Perfection]
Poor communication [see Poor communication]
Poor control and reporting [see Poor control and reporting]
Poor delegation [see Poor delegation]
Poor information [see Poor information]
Poor leadership [see Poor leadership]
Poor planning [see Poor planning]
Poor preparation [see Poor preparation]
Poor self discipline [see Poor self discipline]
Putting things off [see Putting things off]
Resource issues [see Resource issues]
Responsibility, accountability and authority [see Responsibility, accountability and authority]
Socialising [see Socialising]
Staff issues [see Staff issues]
The boss [see The boss]
The telephone 1 [see The telephone 1]
The telephone 2 [see The telephone 2]
Travel time [see Travel time]
Unfinished tasks [see Unfinished tasks]
Unwanted callers [see Unwanted callers]
Work overload [see Work overload]
Your own errors [see Your own errors]
Introduction
Definition of leadership [see Definition of leadership]
Leadership and effectiveness [see Leadership and effectiveness]
Leadership qualities [see Leadership qualities]
Leadership functions [see Leadership functions]
other sites of interest in the series
© Copyright 2011 all rights reserved March Limited

