Introduction
The Risk Management process
Risk issues
Modelling
Events
Networks and branching
Other
The base plan is in place and has been implemented.
This area is all about control.
No plan is foolproof and will probably require some modifications.
Control will require:
All of these activities will run in parallel.
Management will require many aspects including communication, personal and motivational skills.
Empowerment is important. If plans are too rigid in the detail, flexibility is lost and the decision making potential of individuals is reduced.
The higher the experience and skill level of the personnel the greater is the opportunity to have more flexible and less detailed plans.
Monitoring the plan requires the collection of data on its progress and presenting this at regular project team meetings.
In the main, the project team meetings will be conducted by exception.
Progress is usually followed using a Gantt chart which shows tasks as a series of blocks in rows. This is the project schedule.
Modern software e.g. Microsoft Project, is very useful for managing the schedule and look at the affect of various scenarios.
The meetings must encourage openness. The aim is to identify quickly where there are problems and correct them in an appropriate manner.
Naturally, the risk management process should have eliminated major unforeseen circumstances.
However, you can never guarantee that a major problem doesn’t appear and create a crisis.
Dealing with crisis management may not be cost effective especially if you are trying to regain time.
The action plans needed to go beyond the next horizon will need addressing.
To implement these:
Introduction
Definition [see Introduction part 1]
Terminology [see Introduction part 2]
What is a project? Scope [see Introduction part 3]
The processes [see Introduction part 4]
Introduction to processes [see Introduction to processes]
The components [see The components]
Controlling a Stage
Fundamental principles [see Controlling a Stage (CS) part 1]
Authorising Work Package [see Controlling a Stage (CS) part 2]
Assessing Progress [see Controlling a Stage (CS) part 3]
Capturing Project Issues [see Controlling a Stage (CS) part 4]
Examining Project Issues [see Controlling a Stage (CS) part 5]
Reviewing Stage Status [see Controlling a Stage (CS) part 6]
Reporting Highlights [see Controlling a Stage (CS) part 7]
Taking Corrective Action [see Controlling a Stage (CS) part 8]
Escalating Project Issues [see Controlling a Stage (CS) part 9]
Receiving Completed Work Package [see Controlling a Stage (CS) part 10]
Controls
Overview [see Controls part 1]
Project start-up [see Controls part 2]
Tolerance [see Controls part 3]
Product Descriptions [see Controls part 4]
Reports and assessment [see Controls part 5]
Controlled close [see Controls part 6]
Quality
What is quality? [see Quality in a Project Environment]
Purpose and definition [see Configuration management part 1]
Configuration control [see Configuration management part 2]
Project Issue management [see Change control]
Product-based planning [see The techniques]
Benefits [see Product based planning part 1]
Producing a Product Breakdown Structure [see Product based planning part 2]
Writing a Product Description and its contents [see Product based planning part 3]
Creating a Product Flow Diagram [see Product based planning part 4]
Change control steps [see Change control technique]
Overview of the technique [see Quality review technique part 1]
Steps in a formal quality review procedure [see Quality review technique part 2]
Introduction
Foreword [see Foreword]
Purpose [see Introduction part 1]
What does a project manager do? [see Introduction part 2a]
What is it we wish to control? [see Introduction part 2b]
The structure of PRINCE2 [see Introduction part 2c]
What PRINCE2 does not provide [see Introduction part 3]
Directing a project
Purpose [see Directing a project - Purpose]
Objective [see Directing a project - Objective]
Context [see Directing a project - Context]
Activities [see Directing a project - Activities]
Authorize initiation [see Directing a project - Activities - Authorize initiation]
Authorize the project[see Directing a project - Activities - Authorize the project]
Authorize a Stage or Exception Plan [see Directing a project - Activities - Authorize a Stage or Exception Plan]
Give ad hoc direction [see Directing a project - Activities - Give ad hoc direction]
Authorize project closure [see Directing a project - Activities - Authorize project closure]
Managing a stage boundary
Purpose [see Managing a Stage Boundary - Purpose]
Objective [see Managing a Stage Boundary - Objective]
Objective 2 [see Managing a Stage Boundary - Objective 2]
Activities [see Managing a Stage Boundary - Activities]
Plan the next stage [see Managing a Stage Boundary - Plan the next stage]
Update the Project Plan [see Managing a Stage Boundary - Activities - Update the Project Plan]
Update the Business Case [see Managing a Stage Boundary - Activities - Update the Business Case]
Report stage end [see Managing a Stage Boundary - Activities - Report stage end]
Produce an Exception Plan [see Managing a Stage Boundary - Activities - Produce an Exception Plan]
Plans
Purpose [see Plans - Purpose]
What is a plan? [see Plans - Plans defined - What is a plan?]
What is planning? [see Plans - Plans defined - What is planning?]
Levels of plan [see Plans - Plans defined - Levels of plan]
The Project Plan [see Plans - Plans defined - The Project Plan]
Stage Plans [see Plans - Plans defined - Stage Plans]
Team Plans [see Plans - Plans defined - Team Plans]
Exception Plans [see Plans - Plans defined - Exception Plans]
Philosophy [see Plans - The PRINCE2 approach - Philosophy]
Prerequisites for planning - design the plan [see Plans - The PRINCE2 approach - Prerequisites for planning - design the plan]
Define and analyse the products [see Plans - The PRINCE2 approach - Define and analyse the products]
Write the Project Product Description [see Plans - The PRINCE2 approach - Prerequisites for planning - design the plan - Write the Project Product Description]
Create the product breakdown structure [see Plans - The PRINCE2 approach - Prerequisites for planning - design the plan - Create the product breakdown structure]
Write the Product Descriptions [see Plans - The PRINCE2 approach - Prerequisites for planning - design the plan - Write the Product Descriptions]
Create the product flow diagram [see Plans - The PRINCE2 approach - Prerequisites for planning - design the plan - Create the product flow diagram]
Activities [see Plans - The PRINCE2 approach - Identify activities and dependencies - Activities]
Dependencies [see Plans - The PRINCE2 approach - Identify activities and dependencies - Dependencies]
Prepare estimates [see Plans - The PRINCE2 approach - Prepare estimates]
Prepare the schedule [see Plans - The PRINCE2 approach - Prepare the schedule]
Define activity sequence [see Plans - The PRINCE2 approach - Prepare the schedule - Define activity sequence]
Assess resource availability [see Plans - The PRINCE2 approach - Prepare the schedule - Assess resource availability]
Assign resources [see Plans - The PRINCE2 approach - Prepare the schedule - Assign resources]
Level resource usage [see Plans - The PRINCE2 approach - Prepare the schedule - Level resource usage]
Agree control points [see Plans - The PRINCE2 approach - Prepare the schedule - Agree control points]
Define milestones [see Plans - The PRINCE2 approach - Prepare the schedule - Define milestones]
Calculate total resource requirements and costs [see Plans - The PRINCE2 approach - Prepare the schedule - Calculate total resource requirements and costs]
Analyse the risks [see Plans - The PRINCE2 approach - Analyse the risks]
Document the plan [see Plans - The PRINCE2 approach - Document the plan]
Responsibilities [see Plans - Responsibilities]
Risk
Purpose [see Risk - Purpose]
What is a risk? [see Risk - Risk defined - What is a risk?]
What is at risk? [see Risk - Risk defined - What is at risk?]
What is risk management? [see Risk - Risk defined - What is risk management?]
Management of Risk (MoR) principles [see Risk - The PRINCE2 approach - Management of Risk (MoR) principles]
Risk management in projects [see Risk - The PRINCE2 approach - Risk management in projects]
Risk Management Strategy [see Risk - The PRINCE2 approach - Risk Management Strategy]
Risk Register [see Risk - The PRINCE2 approach - Risk Register]
Risk management procedure [see Risk - The PRINCE2 approach - Risk management procedure]
Risk management procedure - Identify part 1 [see Risk - The PRINCE2 approach - Risk management procedure - Identify part 1]
Risk management procedure - Identify part 2 [see Risk - The PRINCE2 approach - Risk management procedure - Identify part 2]
Risk management procedure - Assess [see Risk - The PRINCE2 approach - Risk management procedure - Assess]
Risk management procedure - Plan [see Risk - The PRINCE2 approach - Risk management procedure - Plan]
Risk management procedure - Implement [see Risk - The PRINCE2 approach - Risk management procedure - Implement]
Risk management procedure - Communicate [see Risk - The PRINCE2 approach - Risk management procedure - Communicate]
Risk budget [see Risk - Risk - The PRINCE2 approach - Risk budget]
Responsibilities [see Risk - Responsibilities]
Progress
Purpose [see Progress - Purpose]
What is progress? [see Progress - Progress defined - What is progress?]
What are progress controls? [see Progress - Progress defined - What are progress controls?]
Exceptions and tolerances [see Progress - Progress defined - Exceptions and tolerances]
The PRINCE2 approach [see Progress - The PRINCE2 approach]
The four levels of management [see Progress - The PRINCE2 approach - Delegating authority - The four levels of management]
Project Board controls [see Progress - The PRINCE2 approach - Delegating authority - Project Board controls]
Project Manager controls [see Progress - The PRINCE2 approach - Delegating authority - Project Manager controls]
Use of management stages for control [see Progress - The PRINCE2 approach - Use of management stages for control]
Number of stages [see Progress - The PRINCE2 approach - Use of management stages for control - Number of stages]
Length of stages [see Progress - The PRINCE2 approach - Use of management stages for control - Length of stages]
Technical stages [see Progress - The PRINCE2 approach - Use of management stages for control - Technical]
Event driven and time driven controls [see Progress - The PRINCE2 approach - Event driven and time driven controls]
Baselines for progress control [see Progress - The PRINCE2 approach - Event driven and time driven controls - Baselines for progress control]
Reviewing progress [see Progress - The PRINCE2 approach - Event driven and time driven controls - Reviewing progress]
Capturing and reporting lessons [see Progress - The PRINCE2 approach - Event driven and time driven controls - Capturing and reporting lessons]
Reporting progress [see Progress - The PRINCE2 approach - Event driven and time driven controls - Reporting progress]
Raising exceptions [see Progress - The PRINCE2 approach - Raising exceptions]
Responsibilities [see Progress - Responsibilities]
Introduction
What is a project? [see What is a project?]
What is project management? [see What is project management?]
Project management system [see What does a project management system consist of?]
Project visualisation [see Project visualisation]
Work breakdown [see Why breakdown a project?]
Concept [see Concept or idea]
Feasibility [see Feasibility study]
Initiation [see Initiation]
Specification [see Specification]
Project management design [see Design]
Project management build [see Build]
Project management implementation [see Implementation]
Project management operation and review [see Operation and review]
The Project Notebook [see The Project Notebook]
Plans
Planning [see Planning - part 1]
Planning [see Planning - part 2 – Introduction - need to answer]
Planning [see Planning - part 3 - Introduction - schedule overview]
Plans [see Types of plans]
Detailed planning
Planning [see Detailed planning – part 1]
Estimation [see Detailed planning – part 2 - Initial estimation - simple cost plan]
Estimation [see Detailed planning – part 3 - Initial estimation - high level plan (first review)]
Estimation [see Detailed planning – part 4 - Initial estimation - high level plan (second review)]
Estimation [see Detailed planning – part 5 - Initial estimation - budget cost plan]
Estimating [see Detailed planning – part 6 - Estimating - overview]
Estimating [see Detailed planning – part 7 - Estimating - why are estimates too long?]
Estimating [see Detailed planning – part 8 - Estimating - why are estimates too short?]
Estimating [see Detailed planning – part 9 - Estimating - data usage]
Dependencies [see Detailed planning – part 10 - Dependencies (4 basic types)]
Dependencies [see Detailed planning – part 11 - Dependencies (4 basic types)]
Critical path [see Detailed planning – part 12]
PERT [see Detailed planning – part 12]
Slack and float [see Detailed planning – part 12]
PERT [see Detailed planning – part 13 – PERT – part 1]
PERT [see Detailed planning – part 14 – PERT – part 2]
PERT [see Detailed planning – part 15 – PERT – part 3 - Cumulative Probability graph]
Elapsed time [see Detailed planning – part 16]
Roles and responsibilities [see Detailed planning – part 17]
Responsibilities and resources [see Detailed planning - part 18 - Responsibilities and resources]
Gantt chart [see Detailed planning – part 19]
Constraints [see Detailed planning – part 20]
Critical path [see Detailed planning – part 21 - Critical path – part 1]
Critical path [see Detailed planning – part 22 - Critical path – part 2 - choosing one]
Critical path [see Detailed planning – part 23 - Critical path – part 3 - eliminating one]
Critical path [see Detailed planning – part 24 - Critical path – part 3 - reducing durations]
Project control
Why? What can go wrong? [see Control – part 1 - Why? What can go wrong?]
Monitoring [see Control – part 2 - Monitoring]
General [see Control – part 3 - General]
Scope [see Control – part 4 - What? - scope]
Time [see Control – part 5 - Time]
Cost [see Control – part 6 - Cost]
Cost - common terms [see Control – part 7 - Cost - common terms]
Cost - overspend [see Control – part 8 - Cost - overspend]
Cost - cash flow [see Control – part 9 - Cost - cash flow]
Progress reporting - general [see Control – part 10 - Progress reporting - general]
Progress reporting - Project Board [see Control – part 11 - Progress reporting - Project Board]
Progress reporting - what data? [see Control – part 12 - Progress reporting - what data?]
Taking action - what does this entail? [see Control – part 13 - Taking action - what does this entail?]
Assessing the situation [see Control – part 14 - Assessing the situation]
Resolving issues and problems [see Control – part 15 - Resolving issues and problems]
Contingency [see Control – part 16 - Contingency]
Areas of review [see Control – part 17 - Areas of review]
Controlling change – part 1 [see Control – part 18 - Controlling change – part 1]
Controlling change – part 2 [see Control – part 19 - Controlling change – part 2]
Document control procedures [see Control – part 20 - Document control procedures]
Project completion [see Control – part 21 - Project completion]
Risk management
Risk management [see Risk management – part 1 - Overview]
Risk management [see Risk management part 2 – General approach]
Risk management [see Risk management part 3 – Methods of assessing risk]
Health and safety [see Health and safety]
Project review
Project review [see Project review – part 1 - The benefits]
Project review [see Project review – part 2 - The report]
Introduction
Resources [see Resources]
Workaholic [see Workaholic]
What is time management? [see What is time management? Problem Time solving]
What is time management? [see What is time management? General]
Urgent v important
Urgent v Important 1 [see Urgent v Important 1]
Urgent v Important 2 [see Urgent v Important 2]
Human issues
Human nature [see Human nature]
Blame culture [see Blame culture]
Stress [see Stress]
Stress sources [see Stress sources]
Stress problems [see Stress problems]
Coping with stress [see Coping with stress]
Playtime [see Playtime]
Styles
Time [see Time]
Monochronic time [see Monochronic time]
Polychronic time [see Polychronic time]
High and low context culture [see High and low context culture]
Divergent thinking [see Divergent thinking]
Convergent thinking [see Convergent thinking]
Blending styles [see Blending styles]
Personality drivers [see Personality drivers]
Assertiveness [see Assertiveness]
Delegation
People [see People]
Poor delegation and the Team [see Poor delegation and the Team]
Delegation process [see Delegation process]
Delegation towards independence [see Delegation towards independence]
What not to do [see What not to do]
Key time destroyers
Key Time Destroyers [see Key Time Destroyers]
Action chasing [see Action chasing]
Being disorganised [see Being disorganised]
Cant say 'No' [see Cant say 'No']
Crisis management [see Crisis management]
Desktop management [see Desktop management]
Friends [see Friends]
Large reports [see Large reports]
Low energy levels [see Low energy levels]
Meetings 1 [see Meetings 1]
Meetings 2 [see Meetings 2]
Multiple tasks [see Multiple tasks]
Others errors [see Others errors]
Other's jobs [see Other's jobs]
Paperwork [see Paperwork]
Perfection [see Perfection]
Poor communication [see Poor communication]
Poor control and reporting [see Poor control and reporting]
Poor delegation [see Poor delegation]
Poor information [see Poor information]
Poor leadership [see Poor leadership]
Poor planning [see Poor planning]
Poor preparation [see Poor preparation]
Poor self discipline [see Poor self discipline]
Putting things off [see Putting things off]
Resource issues [see Resource issues]
Responsibility, accountability and authority [see Responsibility, accountability and authority]
Socialising [see Socialising]
Staff issues [see Staff issues]
The boss [see The boss]
The telephone 1 [see The telephone 1]
The telephone 2 [see The telephone 2]
Travel time [see Travel time]
Unfinished tasks [see Unfinished tasks]
Unwanted callers [see Unwanted callers]
Work overload [see Work overload]
Your own errors [see Your own errors]
Strategies
Typical process [see Typical process]
Strategies for getting on with it [see Strategies for getting on with it]
Positive thinking [see Positive thinking]
Commitment [see Commitment]
Introduction
Definition of leadership [see Definition of leadership]
Leadership and effectiveness [see Leadership and effectiveness]
Leadership qualities [see Leadership qualities]
Leadership functions [see Leadership functions]
Characteristics
Identifying the leader [see Identifying the leader]
Trust [see Trust]
Integrity [see Integrity]
Respect [see Respect]
Foresight [see Foresight]
Mutual attraction [see Mutual attraction]
Relationships [see Relationships]
Support [see Support]
Empowerment [see Empowerment]
Credibility [see Credibility]
Winner mentality [see Winner mentality]
Leadership expansion [see Leadership expansion]
Personal development
Proactivity [see Proactivity]
Proactive behaviour [see Proactive behaviour]
Personal direction [see Personal direction]
Personal direction - generating ideas [see Personal direction - generating ideas]
Skill development [see Skill development]
Delegation [see Delegation]
Values [see Values]
Personality traits
Personality - general [see Personality - general]
Personality - action [see Personality - action]
Myers Briggs Type Indicator [see Myers Briggs Type Indicator]
Myers Briggs Type Indicator uses [see Myers Briggs Type Indicator uses]
Fundamental Interpersonal Relations Orientation – Behaviour (FIRO B) [see FIRO B]
Occupational Personality Questionnaire (OPQ) [see OPQ]
Pathology [see Pathology]
Style spider [see Style spider]
Style spider - choices [see Style spider - choices]
Leadership styles - adverse behaviour [see Leadership styles - adverse behaviour]
The three C's
The three Cs [see The three Cs]
The three Cs - action focus part 1 [see The three Cs - action focus part 1]
The three Cs - action focus part 2 [see The three Cs - action focus part 2]
Be positive
Be positive - issues and action [see Be positive - issues and action]
Be positive - be clever [see Be positive - be clever]
Be positive - when in trouble [see Be positive - when in trouble]
Be positive - project management [see Be positive - project management]
Be positive - change management [see Be positive - change management]
Be positive - communication [see Be positive - communication]
Self discipline [see Self discipline]
Be positive - change [see Be positive - change]
Be positive - attitude [see Be positive - attitude]
Motivation
Motivation [see Motivation]
Motivation Douglas McGregors X and Y theory [see Motivation Douglas McGregors X and Y theory]
Motivation - Abraham Maslow [see Motivation - Abraham Maslow]
Motivation - Frederick Herzberg [see Motivation - Frederick Herzberg]
Motivation - key problems [see Motivation - key problems]
Motivation - people part 1 [see Motivation - people part 1]
Motivation - people part 2 [see Motivation - people part 2]
Communication
Open questions [see Open questions]
Meetings [see Meetings]
Agenda [see Agenda]
other sites of interest in the series
© Copyright 2011 all rights reserved March Limited

